CAPITAL IMPROVEMENT PROJECT:

Town & Country Village Sidewalk & Landscape Improvements

Project Description: This project will widen the sidewalks on the north side of Mainstreet in front of Town & Country Village. It also includes much-needed landscape improvements.
Project Cost: $1.5M
Design Phase Completion: January 2022
Construction Begins: June 2022
Project Completion: December 2022


What is happening?

  • Goal is to match the streetscape to downtown

  • Widening of Sidewalk to 12 feet

  • Planting of a tree lawn

  • Addition short retaining wall

  • Construction of decorative fencing

  • Addition of trees in the HOA's grassy area

  • Construction completed by the Town

 